Commuter trains between Aventura and Fort Lauderdale, with a stop in Hollywood, have moved a step closer. The Federal Transit Administration approved Broward Commuter Rail South into its Engineering phase on Oct. 23, 2026, the stage in which the design is taken to completion. Broward County Transit's timeline has trains carrying passengers in 2032.
The line
The project adds 10.5 miles of commuter rail on the existing Florida East Coast Railway, running from the passenger station in Aventura north into Fort Lauderdale. It will have three new stations in Broward County:
- Hollywood. Riders will park in an existing city-owned garage.
- Fort Lauderdale-Hollywood International Airport, giving travelers a train to their flight.
- South Fort Lauderdale, with a new parking garage. The county says this stop serves downtown Fort Lauderdale, Broward Health Medical Center, the Broward County Convention Center, Port Everglades and the beaches.
The project also buys the locomotives and coach cars to run the service. In Miami-Dade, seven more stations are planned on the same corridor through the county's Northeast Corridor project, which would connect the line to Downtown Miami.
What riders get
Broward County Transit says the trip will save 20 to 50 minutes compared with driving I-95. Trains will have level boarding, so riders with strollers, luggage or wheelchairs step straight on, and stations will have audio, visual and digital navigation tools along with fare gates, dedicated safety staff and around-the-clock camera coverage.
How it got here
The line grew out of the Coastal Link study, which looked at 85 miles of commuter rail through Miami-Dade, Broward and Palm Beach counties. The Florida Department of Transportation and Broward County Transit began studying the Aventura to Fort Lauderdale stretch in January 2021, and the Broward County Commission adopted the route on Aug. 25, 2022.
The FTA accepted the project into Project Development on Dec. 2, 2022. In 2024 the project completed its federal environmental review with a Finding of No Significant Impact, along with 30 percent design plans. The county asked to move into Engineering on Oct. 8, 2025, and the FTA approved that request on Oct. 23 of this year.
What comes next
- 2027 to 2029: Engineering. The design is taken to 100 percent, including stations, parking and the maintenance facility.
- 2029 to 2032: Construction. Stations, parking and maintenance facilities are built, and locomotives and coach cars are delivered and tested.
- 2032: Service starts.
Broward County Transit takes public comments and questions on the project. Reach the project team at [email protected], or call project manager Jie Bian at 954-357-8532.